Overall site view of the air traffic control tower under construction in Accra
Overall site view of the air traffic control tower under construction in Accra

Air Traffic Control Tower,
Accra, Ghana

The new air traffic control tower in Accra was constructed to replace the existing structure and strengthen Ghana’s aviation infrastructure. The project demanded precision and scheduling discipline, with a targeted pour height of 3 metres per week.

Location
  • Overall site view of the air traffic control tower under construction in Accra

  • View looking up at the curved concrete wall of the air traffic control tower in Accra. The VARIO and CB240 climbing systems provided precise alignment and safe access at each lift during construction.

  • Ground-level view showing the assembly area and the climbing formwork in operation. The PERI VARIO, CB240, and BR systems enabled efficient six-day cycles for 3 metre pours.

Project Requirements

Related products

Are you working on a project like this?

Call us on +27 (0)21 880 7777 to discuss your requirements further