Internal view of resevoir walls. Neat high concrete finish of walls. Personnel show shear height of resevoir walls

Project Overview

Together with our customers we create great things. Whether scaffolding, skyscrapers, bridges or tunnels, we will show you which projects we have realized together with our customers.

All Projects

 SWARTLAND EIENDOMME New Head Office
Ivory Coast water treatment plant.
 An overview of the site
Ngewelezane Hospital
N7 Malmesbury Bridge
Zimbali Suites
PERI Centurion offered a complete package for Trencon Construction, by providing design, site supervision and transport in addition to supplying a range of PERI products and conventional equipment for the various solutions required to successfully construct this intricately designed structure.
VARIO for pedestrian bridges on the N17 in Ekurhuleni, Gauteng
Maxwell Parkade and Bridge
I-Beams used to span the road to not interrupt traffic flow
Simon Vermooten Bridge
Umlodti Bridge
THEMBALETHU INTERCHANGE
Recharged Aquifer Project
Improved Safety = Faster Slab Turnaround
Alex Mall
Quickstage used as support and access
Total formwork solution for upmarket apartment building
Efficient formwork solutions for port terminal storage areas
Nsezi Reservoir
The new BMA medical centre will be the tallest building in Richards Bay
Growthpoint Properties and Illovo Sugar Head Office
CCI Call Centre
Largest single commercial development in Africa
IDZ Yekani
Slabs formed with PERI MULTIFLEX
Combination of SKYDECK and MULTIFLEX used on the complex slabs
N2 Kokstad Interchange Project
Ghana Revenue Authority Head Office<br/>
Crossings Shopping Complex
The Dune Project
A unique suspended slab-support system was designed for this project.  A travelling gantry was designed to meet the unique time and labour requirements for this project.
The speed of SKYDECK allowed for large pours with low cycle times
Barlow Park
Toyota Richards Bay
Bisho Offices
Creative formwork for Sasol’s new head office in Sandton
First RCS project in South Africa
Bisho offices phase 2
MALMESBURY MALL, WC
Refinery&amp;PlattekloofInterchange,N7,CapeTown
SwartKlip Filter plants
Kumafilila 1.5 ML reservoir cluster 5
A groundbreaking mixed-use project in the Heart of the Mother City
Overview of site
The formwork carriage has been designed so that trucks can pass through at any time without obstacles. Due to the cramped site conditions, an absolutely essential requirement for the execution.
For construction of the emergency parking bays, the formwork carriage was designed with a width of 14.30 m. Moving the carriage to the next bay through the smaller-sized standard cross-section, required a reduction in the maximum external dimensions.
Two steel arches, each with a span of 148 m, carry the middle section of the Waldschloesschen Bridge 26 m above the Elbe.
Simple connecting means and the compatibility of the VARIOKIT Engineering Construction Kit with the PERI UP Modular Scaffolding have facilitated safe access and working platforms in all areas.
Thanks to the detailed planning provided by PERI engineers and high flexibility of the PERI balanced cantilever equipment, the superstructure of the cable stay bridge could be completed according to the schedule.
The 258 m long and 50 m high arched bridge crosses the Opamo Valley in the Bohemian Forest.
Up to 30 m high VARIOKIT VST heavy-duty shoring towers served as falsework for the construction of the bridge edge sections. Each leg carried a load of around 600 kN.
Using a combination of ACS self climbing technology and the VARIO GT 24 girder wall formwork, a solution was developed which was crane-independent as well as ensuring maximum safety in all types of weather.
The VARIOKIT formwork carriage ensured rapid concreting sequences for the construction of the new subway station in Seattle. HD 200 heavy-duty props served as temporary support for the longitudinal edge beams.
The 22.25 m wide superstructure sections were constructed with section lengths ranging from 3.40 m to 4.10 m in regular 10-day cycles.
The 3rd Bosphorus Bridge has the highest concrete bridge piers in the world, and will eventually connect the European and Asian continents after its completion in 2015.
Only when seen from an aerial perspective is the scale of the construction site really apparent: the area is the size of around 2,000 football pitches.
The 180 m long tunnel elements are cast in eight individual segments each 22.50 m long – monolithic, without ties and in compliance with strict dimensional tolerances.
In the complex area with an extremely tight outer radius, the concentrated loads of the radially-arranged cantilever brackets are transferred into the available bridge piers by means of pressure supports.
The Lekki Ikoyi Bridge in Lagos is the first cable-stay bridge in Nigeria.
The VARIOKIT tunnel formwork solution accelerated construction of the 228 m long Marchlehner gallery situated at a height of 1,800 m above sea level. The competent planning process took into account al possible project requirements which ensured on-schedule completion before the onset of winter.
The Midfield Terminal Complex is the ultimate in construction sites: in order to maintain the tight construction schedule, PERI planned and delivered the formwork and scaffolding systems, and has provided yet another convincing performance through the competent engineering service and provision of huge quantities of materials at short notice.
The Algerian metro station &quot;Place des Martyrs&quot; is 144 m long and features record-breaking dimensions with its 23 m width and 14.80 m height.
A VARIOKIT cantilevered parapet carriage serves for constructing the external cantilevered parapets. The horizontal loads are transferred via friction, anchoring is not required.
With some supplementary system components, the VARIOKIT engineering construction kit can also be used for the balanced cantilever construction method. For the construction of the motorway bridge near Tarnow, the construction crew achieved a 4 to 5-day cycle thanks to the easy to use, mechanical solution. At the same time, the high requirements concerning the very small tolerances for the variable bridge cross-sections could be fulfilled.
Designed by Zaha Hadid, the new station – a construction consisting of concrete, glass and steel in the form of a bridge – is characterized by numerous curved shapes. Traffic flows from travelers inspired the architect to create this extraordinary shape.
The LGS Weather Protection Roof on the basis of the PERI UP Scaffolding System made the roof renovation independent of the weather. The 90 m long protection roof consisted of 3 m wide and nearly 30 m long LGS segments.
Accelerated refurbishment project: the customized project solution was based on two compatible PERI modular construction systems – VARIOKIT and PERI UP.
Overall view of the museum complex. Through the TRIO panel formwork, the high requirements on the concrete surfaces have been fully met.
PERI engineers from Greece and Germany worked closely together to develop the shoring solution for the canopy of the new cultural centre – a magic carpet that appears to float just above the building. Solar modules supply the building with &quot;green&quot; energy.
The tent-like roof construction reached a height of 77 m. For the up to 32 m high PERI UP Rosett shoring towers, adapting to the complex roof geometry was carried out using system components from the VARIOKIT engineering construction kit.
The museum shape symbolizes a traditional village hut, which gradually crumbles into dust. Numerous offsets and inclined surfaces characterize the complex structure. PERI engineers developed a customized formwork concept in order to carry out the project with a minimum quantity of special formwork.
For realising the extraordinary museum on time and within budget, PERI planned, produced and delivered over 3,500 customised special formwork elements.
The 33 m high and 60 m long sculpture ensemble, featuring Pegasus and a dragon, was realised in a larger than life size. With the help of the PERI UP solution, more than 1,000 bronze castings could be assembled and welded on site.
With formwork and scaffolding systems perfectly matched each structural component, the concrete frame could be completely finished in only 9 months.
With the help of the customized PERI formwork and scaffolding solution, a new campus complex is being realized in Lima – with high architectural requirements and a tight construction schedule.
The outside of the building resembles a medieval fortress. The facade is comprised of window openings as well as pre-determined regular tie points and horizontal pilaster strips.
The first of a total of three sections will become operational in the autumn of 2017.
Through the planning and supply of formwork and scaffolding from one source, the MULTIFLEX slab formwork and PERI UP shoring could be perfectly matched.
The VARIOKIT heavy-duty shoring towers with a height of 23.60 m can support loads of over 200 t in each case. The horizontal assembly of the approx. 10 m high tower sections makes the erection of the shoring easy and safe.
Cost-effective PERI climbing concept: with a complete platform level and halved on-site wall formwork requirements, fast and continuous working operations were achieved.
The two-storey supporting structure, with a height of 25 metres, accommodates the sorption installation for the flue gas desulphurisation.
Only 7 months after beginning the excavation and foundation work, the topping-out ceremony took place; 8 months later, production started in August 2009.
A total of 9 circular piers with 3.60 m diameters and 40 cm wall thicknesses will subsequently carry a steel platform for the condenser.
Vallirana Tunnel Barcelona, Spain
Entrance of the special steel formwork carriage into the tunnel
The three ITS high-rise towers for the centre of the ambitious Barangaroo South project in the Sydney harbour area.
The ISET Tower in Yekaterinburg is characterized by its external shape. PERI planned a comprehensive, crane-independent concept of the climbing formwork required on the elevator shafts and core walls, as well as the climbing protection panel on the building´s outer edges.
A complete solution consisting of formwork, scaffolding and related services has guaranteed safety at all heights and rapid progress during the construction of JKG Tower complex.
The PERI UP scaffolding extended upwards on the outside keeping pace with the construction progress.
With a height of 220 m, the new office tower of the &quot;Warsaw Spire&quot; building ensemble will be the tallest office building in Warsaw after completion. Two office buildings flank the tower, each 55 m high.
PERI supplied a project-specific formwork and scaffolding solution and supported with comprehensive engineering services for the construction of the 108-m-high complex dam on the River Tua in Portugal.
The Smithland hydroelectric power plant is equipped with 3 turbines; due to the extremely tight construction schedule, all three tubes with their constantly changing cross-sections are being realized at the same time.
Water Towers, Togo
Kamuzu-Dam Overview
The 2.00 m wide shoring scaffold sections are connected longitudinally by means of heavy-duty spindles and push-pull props to form shoring towers.