The Project
Impressions from the project process
Project Information
Requirements
The bridge replaced the previous unsafe low-level causeway. There are two river crossings associated with this project - the Umhlanga and Umdloti Rivers. The expansion also required the widening of the roadway by approximately 7.5m at select points along the freeway.
Solutions
Group Five chose PERI VARIO for the incremental launch formwork on the project. VARIO shutters allowed Group Five to utilise two sets of shutters for the same price as one set of conventional steel shutters, which meant that they could cast the south and north bound sections simultaneously. The massive piers were poured in 8.1 m increments using PERI TRIO with customised box-outs to create the recess in the concrete. CB Brackets were used as access platforms to replace temporary bearing platforms with permanent ones.


Warren Dalais
Site Engineer
For the piers, the TRIO box out shutters worked extremely well.