The Kariba Plunge Pool Reshaping project, undertaken by Razel-Bec. The project involved the meticulous reshaping of the plunge pool at the Kariba Dam, an essential infrastructure upgrade to ensure the dam's continued safety and functionality. Key activities included the installation of piers, construction of a coffer dam, and extensive dewatering efforts .
Location
Project participants
Specialist Contractor: Razel-Bec
-
Second Pier , full volume pour -
Pier 3 under the move-in plunge pool beneath the dam wall, -
Pier 3 being floated off submerged lift into plunge pool area -
Pier 2 in place preparing for 2400 mm pour -
View of the coffer dam from the plunge pool side -
20 meters deep from the water level at the bottom of the hole -
concrete base establishment -
Fault line concreted closed -
Kariba plunge pool refilled